District eyes 2015 opening for water plant

Sicamous residents and businesses will likely be waiting until 2015 before they have a clean, reliable source of municipal water.

Sicamous residents and businesses will likely be waiting until 2015 before they have a clean, reliable source of municipal water.

At the Oct. 9 district committee of the whole meeting, council heard from Timothy Phelan, senior project manager with Opus DaytonKnight Consultants Ltd., regarding the recently completed Mara Lake water treatment plant feasibility study.

Following Phelan’s report, Coun. Fred Busch asked the question he is frequently asked by residents: when will the new $4.5 million water treatment facility be up and running.

“I guess my question that really concerns me is, are we on schedule, not that there ever really was a schedule, but are we on some sort of schedule that we’re going to be able to delivers this plant in the middle of the summer 2014 – at the latest fall 2014?” asked Busch.

District operations manager Randy Hand explained there have been several delays getting started, and that the district is doing its best to get on track.

“And we’re approaching it at this time with just baby steps,” said Hand. “We’ve also had some funding limitations, in large around the parameters for funding… we’re just getting that information now.

“This feasibility study was the next step we wanted to take in order to get some of the costs on some of these items.”

Hand said he wouldn’t expect the plant to be up and running until 2015, adding staff do not want it starting up during peak season (summer), so as to allow time to work out issues around training, staffing, etc.

“I guess if that’s the way it has to be, but that’s not what we were told initially, that it would be (ready in) 2014,” replied Busch.

According to as summary of findings and conclusions from the study, the membrane filtration system that’s being tested by the district will meet Interior Health Authority treatment requirements. Based on 2.7 per cent population growth – the highest rate projected in the district’s official community plan –  for a 20-year period, the plant would be designed to provide eight megalitres a day, yet be expandable to 10.

The report touches on treatment of waste from the filtration process. It recommends against discharge into Mara Lake. It does note, however, that the facility site would have space for a solids storage pond.

“(We) looked at that and there is enough space to have some sort of evaporation concentration of solids so that a majority of the solids can be kept on site without going to the collection system,” said Phelan.

Busch asked if this would create an odour problem, but Phelan said he didn’t expect there would be any.

The report also provides four options based on total estimated construction costs, including a 15 per cent contingency.

The least optimized option is expected to cost $4,737,000, the highest, $6,065,000.

Council was to have a separate, in-camera meeting to discuss the options.

The federal and provincial government’s have committed to funding one-third each of the original estimated cost of $4.5 million, the district is responsible for the remainder.

 

Just Posted

Alternative approval process to proceed for Centennial Field purchase

Fate of loan to purchase land for future park in hands of South Shuswap residents

Valdy gives volunteers a hand after Salmon Arm Roots and Blues Festival

Celebrated Canadian singer pitched in alongside starstruck clean-up crew

Robbery tactic used on Salmon Arm senior not uncommon

RCMP advice comes after credit cards stolen at Walmart parking lot

Salmon Arm Roots and Blues Festival exceeds expectations

Artists, attendees and organizers praise effort behind successful event

Founder of Salmon Arm’s sister city exchange helps welcome Inashiki visitors

Twenty three Japanese guests visit city for a week, Salmon Arm to return in March

VIDEO: Could we BE any more excited? ‘Friends’ fans go crazy for merch

Movie theatres will show select episodes to mark the NBC series’ 25th anniversary

Penticton man sentenced in non-fatal 2017 shooting

Elkena Michael Knauff sentenced to seven and a half months in jail

Bodies of two missing Surrey men found near Ashcroft

Ryan Provencher and Richard Scurr have been missing since July 17

Kamloops RCMP locate and arrest man who fled from police

The 22-year-old male was wanted in relation to a domestic violence investigation

North Shuswap Lions, Celista winery host benefit concert

Sept. 7 event at Celista Estate Winery to support North Shuswap Youth Program

Five hedgehogs quickly adopted after being left at BC SPCA

Lucky new owners picked up their pets from Maple Ridge branch on Aug. 20

COLUMN: Much to enjoy at Ryga Arts Festival

As I learn about George Ryga and his contributions, it is clear why this festival carries his name

Shuswap history in pictures

Shuswap history in pictures: mechanics class

Most Read